Important roadworks information
A14 westbound full closure junction 22 to junction 13 – Patching, pothole repairs and resurfacing
I am writing to tell you that we plan to carry out pavement work on the A14 westbound full closure junction 22 to junction 16. This work is needed to ensure the A14 continues to remain in a safe and serviceable condition.
We plan to complete this work over three shifts starting Thursday 19 March 2026 to Saturday 21 March 2026. We will work between 8pm and 6am, weather permitting.
Closures and diversions
To carry out the work safely, we will need to close the A14 westbound between junction 22 to junction 16 and divert traffic as follows:
Thursday 19 and Friday 20 March 2026
A14 eastbound full carriageway closure between junctions 13 and 22
Local traffic travelling on the westbound carriageway and wishing to cross to the A14 eastbound will be able to do so at the following locations:
- Westbound cross-over point at Woolley (junction 19A)
- Westbound cross-over point at Leighton Bromswold (junction 17)
- Westbound cross-over point at Bythorn (junction 15)
Traffic approaching these junctions will be diverted onto the westbound carriageway and directed to the appropriate cross-over point.
Eastbound diversion:
- Drivers travelling eastbound will be diverted off the A14 at junction 13
- Follow the A605 to the A1(M) at junction 17, then take the A1(M) and A1 southbound to return to the A14 at junction 22
Saturday 21 March 2026
A14 westbound full carriageway closure between junctions 22 and 16
Westbound diversion:
- Drivers travelling westbound will be diverted northbound on the A1 / A1(M) to junction 17
- Join the A605 and follow it to return to the A14 at junction 13