Re: A14 River Nene joint replacement works
I’m writing to inform you of upcoming maintenance work on the A14 River Nene bridge, near Thrapston. We’ll be replacing the bridge joints to provide a safer road, whilst reducing the need for future maintenance.
When will this work take place?
Our work is planned to start on Monday 1st September 2025, and we expect to complete early 2026.
To complete our work safely, we’ll work overnight using a combination of full closures and lane closures to reduce disruption. Our work at this location will also include a series of weekend closures. Further updates will be provided at the earliest opportunity.
Traffic Management
From 1 September to 5 September, A14 closed westbound, 9pm to 5am.
From 8 September to 12 September, A14 closed eastbound, 9pm to 5am.
From 22 September to 26 September, A14 closed westbound, 9pm to 5am.
From 29 September to approximately mid-November, A14 closed eastbound, Monday to Friday, 9pm to 5am.
From approximately mid-November to early 2026, A14 closed westbound, Monday to Friday, 9pm to 5am. No closures will be in place over the Christmas holidays.
We do require two full weekend closures that are currently planned for eastbound in October and westbound in January 2026, exact dates will be confirmed in due course. Throughout this time, we’ll close the road from 8pm on Friday to 6am on Monday morning. These are required for the installations of the new expansion joints.
We’ll also on occasion install daytime lane closures and temporary traffic lights on Denford Road (underneath the A14) to maintain safety.
To maintain safety, a reduced speed limit of 50mph to 40mph will be in place including speed enforcement.
What does this mean for you?
During closures, we’ll install a fully signed diversion
Traffic will be diverted along the A6/A45 between A14 junctions 10 and 13 when closures are in affect.
Access for emergency service vehicles will be maintained throughout.
We’ll make every effort to ensure the impact on the local community and travelling public is kept to a minimum. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes.
Please accept our apologies in advance for any inconvenience this may cause.
Further information
If you’d like to receive updates about future work along the A14, please subscribe to our distribution list by emailing noreplyA14emids@nationalhighways.co.uk. We’ll also use this platform to provide further updates regarding our full weekend closures.
For further information about this work, please contact National Highways Customer Contact Centre on 0300 123 5000 open 24/7, email info@nationalhighways.co.uk, or write to us at National Highways, National Traffic Operations Centre, 3 Ridgeway, Quinton Business Park, Birmingham, B32 1AF.
Further details about our works and future updates will be provided on our website https://nationalhighways.co.uk/our-roads/east-midlands/east-midlands-maintenance-schemes/